基督教芥菜種會新莊愛心育幼院原址,營造『都市共生、青銀共創、社區共學』的整合福利園區,預計於2026年與大家見面。


%%{init: {'theme':'neutral'}}%%
gantt
    title 芥菜種會大樓施工進度表(112年)
    dateFormat YY-MM-DD
    建照變更核准(112.01.18) : milestone, m1, 23-01-18, 1d
    section 地工工程
    連續壁(壁樁) : done, des1, 23-03-02, 23-07-22
    基樁(含樁底灌漿) : done, des2, 23-07-24, 23-12-31
%%{init: {'theme':'default'}}%%
gantt
    title 芥菜種會大樓施工進度表(113~114年2月)
    dateFormat YY-MM-DD
    鋪面破碎 (02.16) : milestone, m1, 24-02-16, 1d
    一階(構台)完成 (03.20) : milestone, m2, 24-03-20, 1d
    二階完成 (04.20) : milestone, m2, 24-04-20, 1d
    三階完成 (05.20) : milestone, m2, 24-05-20, 1d
    開挖完成 (06.22) : milestone, m2, 24-06-22, 1d
    接地工程 (07.11) : milestone, m3, 24-07-11, 1d
    基礎版澆置 (08.17) : milestone, crit, 24-08-17, 1d
    地梁澆置 (08.28) : milestone, crit, 24-08-28, 1d
    B3FL澆置 (09.13) : milestone, crit, 24-09-13, 1d
    3rd 支撐拆除 (09.20) : milestone, m3, 24-09-20, 1d
    B2FL澆置 (10.30) : milestone, crit, 24-10-30, 1d
    2nd 支撐拆除 (11.06) : milestone, m3, 24-11-06, 1d
    B1FL澆置 (12.07) : milestone, crit, 24-12-07, 1d
    1st 支撐&構台拆除 (12.14) : milestone, m3, 24-12-14, 1d
    連續壁劣質混凝土打除 (12.23) : milestone, m3, 24-12-23, 1d
    1FL澆置(全棟)(02.27) : milestone, crit, 25-02-27, 1d
    section 擋土支撐
    中間柱埋設 : done, des1, 24-01-11, 24-02-05
    section 擋土支撐
    擋土支撐-土方開挖 : done, des2, 24-02-06, 24-06-22
    section 結構工程
    地下結構體 : done, des3, 24-06-24, 25-02-28
%%{init: {'theme':'default'}}%%
gantt
    title 芥菜種會大樓施工進度表(114~115年)
    dateFormat YY-MM-DD
    
    1FL澆置(全棟)(02.27) : milestone, m1, 25-02-27, 1d
    2FL澆置(BC棟、A棟-梁)(05.08) : milestone, crit, 25-05-08, 1d
    3FL澆置(BC棟)(06.07) : milestone, crit, 25-06-07, 1d
    3FL澆置(A棟)(06.10) : milestone, crit, 25-06-10, 1d
    4FL澆置(BC棟)(07.01) : milestone, crit, 25-07-01, 1d
    4FL澆置(A棟)(07.03) : milestone, crit, 25-07-03, 1d
    5FL澆置(A棟)(07.25) : milestone, crit, 25-07-25, 1d
    5FL澆置(BC棟)(07.26) : milestone, crit, 25-07-26, 1d
    6FL澆置(A棟)(08.15) : milestone, crit, 25-08-15, 1d
    6FL澆置(BC棟)(08.18) : milestone, crit, 25-08-18, 1d
    7FL澆置(A棟)(09.05) : milestone, crit, 25-09-05, 1d
    7FL澆置(BC棟)(09.10) : milestone, crit, 25-09-10, 1d
    8FL澆置(A棟)(09.25) : milestone, crit, 25-09-25, 1d
    8FL澆置(BC棟)(10.01) : milestone, crit, 25-10-01, 1d
    9FL澆置(A棟)(10.13) : milestone, crit, 25-10-13, 1d
    9FL澆置(BC棟)(10.23) : milestone, crit, 25-10-23, 1d
    10FL澆置(A棟)(11.04) : milestone, crit, 25-11-04, 1d
    10FL澆置(BC棟)(11.12) : milestone, crit, 25-11-12, 1d
    11FL澆置(A棟)(11.22) : milestone, crit, 25-11-22, 1d
    11FL澆置(BC棟)(12.02) : milestone, crit, 25-12-02, 1d
    12FL澆置(A棟)(12.10) : milestone, crit, 25-12-10, 1d
    12FL澆置(BC棟)(12.23) : milestone, crit, 25-12-23, 1d
    13FL澆置(A棟)(12.29) : milestone, crit, 25-12-29, 1d
    13FL澆置(BC棟)(01.12) : milestone, crit, 26-01-12, 1d
    RFL澆置(A棟)(01.20) : milestone, crit, 26-01-20, 1d
    RFL澆置(BC棟)(02.02) : milestone, crit, 26-02-02, 1d
    R2FL澆置(A棟)(02.09) : milestone, crit, 26-02-09, 1d
    R2FL澆置(BC棟)(03.02) : milestone, crit, 26-03-02, 1d
    R3FL澆置(A棟)(03.11) : milestone, crit, 26-03-11, 1d
    R3FL澆置(BC棟)(03.16) : milestone, crit, 26-03-16, 1d
    屋突完工(全棟)(03.27) : milestone, crit, 26-03-27, 1d
   
    section 結構工程
    1F(2/28~5/8) : done, des1, 25-02-28, 25-05-08
    2F(5/9~6/10) : done, des2, 25-05-09, 25-06-10
    3F(6/8~7/3) : done, des3, 25-06-08, 25-07-03
    4F(7/2~7/26) : done, des4, 25-07-02, 25-07-26
    5F(7/26~8/18) : done, des5, 25-07-26, 25-08-18
    6F(8/16~9/10) : done, des6, 25-08-16, 25-09-10
    7F(9/6~9/30) : done, des7, 25-09-06, 25-09-30
    8F(9/26~10/23) : done, des8, 25-09-26, 25-10-23
    9F(10/14~11/12) : done, des9, 25-10-14, 25-11-12
    10F(11/5~12/2) : done, des10, 25-11-05, 25-12-02
    11F(11/23~12/23) : done, des11, 25-11-23, 25-12-23
    12F(12/11~01/12) : done, des12, 25-12-11, 26-01-12
    13F(12/31~02/02) : done, des13, 25-12-31, 26-02-02
    RF(1/24~03/27) : done, des14, 26-01-21, 26-03-27

芥菜種會大樓工程《施工紀實》